Pricing a builder's pipeline.

One builder, eight projects priced in four months. 3D scheme model
3D scheme model
One builder, eight projects priced in four months. Shell
Shell
One builder, eight projects priced in four months. Complete
Complete
Builder partner · Extensions & retrofits · Dublin & Kildare

One builder, eight projects priced in four months.

A growing residential contractor uses EchoByld to cost plan, de-risk and win its pipeline, from compact terraced extensions to a whole house retrofit. Where homeowners awarded the build through EchoByld, the same chartered engineer certified the work.

€1.39mof residential work cost planned for one builder (8 projects, May to Aug 2026)
+19%floor area missing from an architect's tender schedule, caught before pricing
2.5%final certified cost against the EchoByld cost plan on a completed closed loop extension
The challenge
A growing Dublin builder was pricing everything from small ICF extensions to deep retrofits with steel frames, heat pumps and occupied house phasing. Estimating time was the bottleneck, and the tender packs it received were not always right.
What EchoByld did
Platform takeoffs turned drawings into trade by trade contractor cost reports, with provisional sums and risk allowances, plus a plain English cost plan the builder could share with the homeowner. On one architect led tender, EchoByld re-measured the drawings: the schedule understated the floor area by 29 m² (19%), so the builder could qualify its price instead of absorbing the loss. Where the homeowner awarded the contract, EchoByld stayed on as chartered structural engineer for inspections, lender stage certificates and the final Opinion on Compliance.
The outcome
Eight projects cost planned in four months. The first completed closed loop extension was certified at €128,162 against a €125,000 plan, with nothing outstanding at handover.
Tender review

Gaps found before pricing.

A representative groundworks tender review. Names, locations and figures are changed to protect client confidentiality.

Business park site development · Leinster · ~€1.0m tender

A €1.03m groundworks tender, corrected before pricing.

Drawings, bill of quantities and specification read against each other, so the gaps surfaced before a single rate was entered.

+€210kadded to the stated tender base (+20.5%)
€76kpreliminaries priced at a nominal sum
81%scope completeness, with every gap listed
12draft RFIs ready to issue before tender close
PRELIMINARIESHIGH
€18,500 lump sum for a 26 week programmeCorrected allowance of €76,000 built from the documents.
UTILITY DIVERSIONSHIGH
Scope split with the network operator unresolved€29,500 adopted. Confirm the split before pricing.
DRAWING VS BILLCONFLICT
Surfacing specified as SMA on drawing, HRA in the bill€11,880 differential priced and RFI drafted.

Representative example. Names, locations and figures changed to protect client confidentiality.

Cover of an EchoByld sample report extract
Sample report extract · Groundworks

See exactly what an EchoByld report contains.

Executive summary, costed risk register with proposed corrections, and an ARM4 / NRM2 style bill of quantities extract from the same site development tender.

6pages from a full report
10costed risks with corrections
54measured BoQ lines, tagged by confidence
12draft RFIs

Sample extract. Project, client, drawings, quantities and rates are fictional, for illustration only.

For homeowners

Family homes, delivered with confidence.

Derelict bungalow to family home, grant funded and signed off. Before
Before
Derelict bungalow to family home, grant funded and signed off. Progress
Progress
Derelict bungalow to family home, grant funded and signed off. After
After
Homeowner · Derelict property restoration · West Wicklow

Derelict bungalow to family home, grant funded and signed off.

A long vacant rural bungalow needed a structural case, a costed scope and a grant application that would stand up to council scrutiny. EchoByld delivered all three, and the full grant was approved.

€70,000Vacant Property Refurbishment Grant plus derelict top up approved, the maximum available
12structural defects recorded (4 critical), each closed out with before and after evidence
47vouched items in the drawdown claim
The challenge
The house had stood empty for years: a moss covered roof, a ceiling collapsed into the roof void, a cracked chimney, and damp and mould in every room. The owner needed to prove it qualified, show what restoration would take, and do both in a form the council would fund.
What EchoByld did
A chartered structural engineer inspected the house and logged every defect. EchoByld drew the existing and proposed layouts, produced a grant ready bill of quantities, secured a Section 5 declaration that the works were exempt from planning, and assembled the full application. On completion it prepared the drawdown claim and a close out report pairing every defect with its repaired condition.
The outcome
The full €70,000 grant was approved in May 2026 and the works were substantially complete by July.
Read the full story
One tender, read properly. Before
Before
One tender, read properly. Design visualisation
Design visualisation
One tender, read properly. Steel frame
Steel frame
One tender, read properly. As built
As built
Homeowner · Steel framed extension & garden office · North Kildare

One tender, read properly.

A family's only tender looked €6,000 over budget. Counting the exclusions and open ended provisional sums, it was really €15,000 over. EchoByld's review found the gaps and gave the family a clear negotiation plan.

€305ktrue cost of the tender once exclusions were counted (headline €296k)
€27.7kof above market preliminaries and an open heating allowance flagged
5structural revisions to verify the fabricator's steel before it reached site
The challenge
The homeowners wanted a vaulted, steel framed rear extension and a glazed garden office within a firm budget. Only one builder returned a price, and at first glance it looked close enough to sign.
What EchoByld did
EchoByld compared the quote line by line with its own cost plan. Site supervision was priced well above market, heating was a placeholder sum, the specified sliding door couldn't be supplied, and inspections and the BER were excluded. EchoByld set out options and the exact clarification questions to send, designed the junction with the existing hipped roof, and checked the fabricator's steel drawings before fabrication.
The outcome
A clarified, revised contract sum was agreed. The steel frame went up in August and the glazed gable was weathertight by late September.
Switching to ICF without moving the price. Before
Before
Switching to ICF without moving the price. 3D model
3D model
Switching to ICF without moving the price. ICF walls before pour
ICF walls before pour
Switching to ICF without moving the price. As built
As built
Homeowner · Single storey ICF extension · South Dublin

Switching to ICF without moving the price.

The builder had quoted a traditional block extension. EchoByld re-costed it in insulated concrete formwork and matched the fixed price within 1.5%, while catching a party wall item nobody had priced.

<1.5%EchoByld ICF estimate against the builder's fixed price
€3,973unpriced party wall item identified before work started
12 weeksfrom substructure inspection to practical completion, with no structural remedial work
The challenge
The family had accepted a fixed price for a flat roof extension in blockwork with a separate steel beam. ICF promised better thermal performance and fewer trades, but nobody knew if it would hold the price.
What EchoByld did
EchoByld modelled the scheme in 3D and rebuilt the bill of quantities around ICF walls, which also carried the opening without a separate beam. It reconciled the result line by line against the accepted quote, then, as structural engineer, held four inspections at the critical stages and supported each bank drawdown with stage certificates.
The outcome
The ICF build came in within 1.5% of the original price, passed every hold point and reached practical completion in July 2026.
Client feedback

What clients say.

“EchoByld and John handle all our pricing now. We're going in clear on all our projects and winning more work, faster. Our prices land fully measured with the client first. Speed is winning work, and accuracy is helping us make profits.”

DDominicDublin contractor

“The Pro setup is helping us manage delivery on site. We need a fraction of the admin time and it's saving us 10+ hours a week, easily. That's time to focus on delivery instead of measuring and paperwork.”

HHousing developerPro plan
★★★★★

“EchoByld has been very easy to use and gave me excellent peace of mind when building my house. All elements regarding the final list of quantities happened straight away giving me a plan to start construction with great confidence and removed all unwanted surprises.”

Jonathan WhelanNew build
★★★★★

“Used EchoByld for our new build house. John looked after everything, very easy to deal with. Everything needed was done in a timely manner and he carried out inspections appropriately. Would definitely recommend.”

Darragh CallaghanNew build
★★★★★

“EchoByld helped out on my vacant property grant application with Wicklow County Council. They handled everything and John was available to discuss any concerns. I also didn't realise that this property might qualify for the Derelict Homes Grant, so there was potential to increase the grant entitlement.”

PatVacant Property Grant, Wicklow

Start with the problem you have today.