Six checks for any subcontract package before it is priced or let. A scope gap isn't always an unmeasured quantity: sometimes the quantity is known, but the responsibility, temporary condition or allowance is not.

5 minutesNo sign upCopy or print your review
Step 1

Choose the package.

Step 2

Work through the six checks.

Mark each prompt Resolved, Unclear or not applicable. Unclear interfaces, temporary conditions and commercial items carry the most weight.

01 Permanent works

Is the complete scope defined?

Frame, glass, gaskets, seals and brackets fully specified and quantified
Design responsibility for the system and its calculations allocated
02 Package interfaces

Who owns each connection?

Glazing to roof waterproofing: who designs and installs the junction
Slab edge fire stopping and bracket fixings: whose package
03 Temporary conditions

Who designs, provides and maintains protection?

Temporary weather protection until the roof and adjoining cladding close
Protection of installed glass from following trades
04 Sequence

Is the priced scope compatible with the programme?

Façade programmed against roof closure and adjoining cladding
Access (MEWP, scaffold, crane) available when the package needs it
05 Commercial ownership

Is the work priced, included or expressly excluded?

Temporary waterproofing priced, included or expressly excluded
Attendance, hoisting and storage allowances agreed
06 Verification

Who inspects, accepts and records completion?

Joint interface inspection before follow on trades
Water testing method, frequency and witnessing agreed